Back to News
Eden Crest After

What We've Learned From Complaints - October Update

Each month, we look at the complaints and service requests we receive. This helps us understand what's going well, what isn't working and where we need to make improvements.

Here's a look at what happened in October 2026 and what we're doing to make things better.

How many complaints did we receive?

In October, we received:

  • 37 Stage 1 complaints (compared with 23 in October last year).
  • 5 Stage 2 complaints (compared with 2 last year).
  • 32 service requests (compared with 70 last year). Service requests are issues that we can fix quickly without needing to progress through the formal complaints process.

From April to October, we received:

  • 181 Stage 1 complaints (compared with 143 last year).
  • 21 Stage 2 complaints (compared with 9 last year).
  • 303 service requests (compared with 416 last year).

When we add together service requests and Stage 1 complaints, the total has fallen from 559 to 484 compared with the same period last year.

However, the number of formal complaints is going up. Stage 1 complaints were 61% higher than in October last year. If this continues, we expect to receive around 10% more Stage 1 complaints by the end of the year than we did in 2025/26.

What does this tell us?

The data shows that fewer customers are making service requests, but more are making formal complaints.

We're providing training to our staff to make sure that service requests are being recorded properly. This is to make sure that the drop in numbers reflects customer satisfaction rather than under-reporting.

We've also looked at all the Stage 2 complaints received during 2026. We'll share what we learned from this review soon.

What are customers telling us?

The main reasons customers complained in October were:

  1. Delays and slow resolution.
  2. Poor communication.
  3. Repairs that needed doing again or weren't finished.
  4. Missed appointments.

Almost half of all the complaints about our service involved some kind of delay.

Communication has also become a bigger issue. It was the fourth most common reason for complaints last month, but has now moved up to second place.

What are we doing about this?

One of our main repairs contractors has had more appointments changed or cancelled. This has led to more complaints from customers.

We've raised this with them at our weekly meetings with them.

We've also seen a small rise in complaints about another contractor. We've found a possible problem with how customers are told about air source heat pump loop systems. We've raised this at our monthly meeting with the contractor.

Most complaints about our own services are about delays and slow progress. This has been an ongoing problem, so we're looking at whether we have enough resources to deal with the work.

How quickly did we respond?

We want to deal with complaints as quickly as possible.

Here's how we did in October:

  • We answered Stage 1 complaints in an average of 2 working days.
  • Our average response time from April to October was 3 working days.
  • This is well within the Housing Ombudsman's target of 10 working days.
  • 100% of customers were happy with how we handled their complaints, both in October and across the year so far.
  • We didn't refuse any complaints in October.
  • The Housing Ombudsman didn't contact us with any enquiries.

We responded to 29 Stage 1 complaints in October. We agreed that something had gone wrong in 18 of these cases.

This shows that when customers tell us something isn't right, they often have a good reason to complain. We need to listen and put things right.

Compensation

In October, we paid £659 in compensation. All of this was for Stage 1 complaints.

Here's what the payments were for:

  • Delays in completing work: £259.
  • Missed appointments: £225.
  • Problems with our processes: £150.
  • Poor communication: £25.

From April to October, we paid £13,718.23 in compensation.

This is less than the £22,158.90 we paid during the same period last year.

Based on the figures so far, we expect to pay around £23,474 in total by the end of this financial year.

When a contractor's work has caused a problem, we ask them to pay back the cost to us.

In October, we charged our contractors £464.

What have we learned?

Looking at our complaints helps us understand what needs to change.

Here are the main things we've learned:

  • Delays are still the biggest problem. Poor communication is also becoming a bigger concern. We know we need to improve both.
  • More customers are making formal complaints. We need to make sure we record problems as soon as customers tell us about them, rather than waiting until they become bigger issues.
  • Contractors need to do better. They must keep appointments and let customers know if anything changes.
  • Complaints can come from anyone, anywhere. We haven't found any clear patterns linked to where people live, their age or their ethnic background.

What are we doing next?

We know we need to keep improving. Here are the steps we're taking. We are:

  1. Asking every service manager to explain what they're doing to improve delays and communication.
  2. Using our weekly and monthly meetings with contractors to make sure they keep appointments and communicate better with customers.
  3. Recovering costs from contractors where their work has caused problems. 
  4. Making sure service requests are recorded properly. We're reviewing staff training and visiting team meetings to explain the process.
  5. Sharing the findings from our review of Stage 2 complaints.
  6. Looking at capacity and more proactive monitoring of customer contacts, so we spot delays before they become complaints.

Your feedback helps us improve

If something goes wrong, please tell us.

We want to hear from you, understand what has happened and do what we can to put things right.

Your feedback helps us learn, improve our services and give you a better experience: Contact Us - North Star Housing Group

Featured Posts

Two men in workwear are servicing a wall-mounted boiler. One man is actively working on the open boiler using tools, while the other observes closely. Various tools are scattered on the countertop below, and a window to the right lets in natural light, showing a red brick wall outside

Winter Weather Update: Emergency Repairs

23 Oct 2026

Please expect longer call wait times during winter

Read Story

Apply For a Home

Find out how to apply for a home with North Star

Apply Now

Manage My Tenancy

Information and advice for tenants

Learn More
Built with ByteEditor